The city built the 2025 mill and overlay with its own crews and equipment, charging no labor or equipment costs, cutting assessments to roughly $1,520 per unit. Contractors — AGC, Brad Schmidt and Steve Marco — sued, arguing such work must be competitively bid; the case is now before the North Dakota Supreme Court. The outcome could determine whether this cost-saving method can ever be used again.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Jun 23, 2026.
Impact analysis
Self-performance kept this mill and overlay's assessments far cheaper than comparable contractor-built overlay projects — potentially half the cost per property.
Residents north of 13th Avenue in the assessment district got a notably cheaper street repair bill.
Contractors who say the practice circumvents competitive bidding laws — and possibly future residents if the court bars the method.
Mentions & discussions (1)
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for City of West Fargo
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.