Summary
Project No. 2293 would build a grade separation where 9th Street NE crosses the railroad. The agenda included overpass and C&M agreements.
At a glance
- Total mentions
- 5
- Last 30 days
- 0
Last discussed Jun 15, 2026.
Impact analysis
Contract value comes from the accepted bid; the cost lands on the city's capital construction budget.
Drivers crossing the tracks on 9th Street NE would avoid train delays.
Mentions & discussions (5)
City Commission - Jun 15, 2026
A change order was scheduled for the 9th St NE grade separation project — the rail/road separation project affecting traffic on the city's northeast side.
City Commission - May 4, 2026
Construction material testing services with Braun Intertec were approved for the 9th Street corridor projects, moving the grade separation and reconstruction forward.
City Commission - Apr 20, 2026
The commission accepted the bid and awarded the contract for a grade separation on 9th Street NE — a major rail/traffic safety project. Construction should reduce conflicts where the road crosses the railroad.
City Commission - Apr 6, 2026
Project No. 2293 would build a grade separation where 9th Street NE crosses the railroad. The agenda included overpass and C&M agreements.
City Commission - Feb 2, 2026
The city moved forward with the 9th Street NE grade separation — a project to separate road traffic from the railroad tracks. The engineer's report is now approved and design work begins.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for City of West Fargo
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.